Tender Profit Summary

Job Code

Jim

Date

6-18-2026
DescriptionNett MaterialGeneral Profit MaterialExtra Overall Profit - MaterialTotal Materials GrossHours LabourNett LabourGeneral Profit LabourExtra Overall Profit - LabourTotal Labour GrossPrelimsBuilders DiscountPrime Costs / Provisional SumsTotal Labour & Materials
1 Unassigned Section 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 New Section 850.00 0.00 0.00 850.00 366.60 38,602.98 0.00 0.00 38,602.98 0.00 0.00 0.00 39,452.98
3 New Section1 850.00 0.00 0.00 850.00 21.60 2,274.48 0.00 0.00 2,274.48 0.00 0.00 0.00 3,124.48
1,700.000.000.001,700.00388.2040,877.460.000.0040,877.460.000.000.0042,577.46